Long Term Service Agreements (LTSA`s)
Support services
negotiation
re-negotiation
operation
avoiding the pitfalls
energy-i work
with, advise and assist our clients on negotiating and re-negotiating Long Term
Service Agreements (LTSAs).
energy-i are
experts in negotiating and implementing LTSAs which seamlessly transition from
EPC phase to operational phase of a plant lifecycle, and crucially meet the
requirements of financiers and lenders.
energy-i are
experts in negotiating and implementing innovative LTSAs from Independent
Services Providers (ISPs) to provide levels of service which equal or exceed
Original Equipment Manufacturer (OEM) LTSAs.
An LTSA what is
it?
A gas turbine Long Term Service Agreement (LTSA) is a
commercial contract between a power plant Owner and an Original Equipment
Manufacturer (OEM) or Independent Service Provider (ISP), outlining the split
of operational, maintenance, and financial responsibilities over the lifecycle
of the gas turbine based plant.

Turbine Maintenance
Repair Overhaul (MRO)
The
global market for gas turbine maintenance, repair, and overhaul (MRO) services
is projected to exceed USD$35 billion (EURO 31.15 bn) by 2030.
Why?
An
ageing fleet of E and F class gas turbines globally which are being retained in
service as necessary dispatchable back-up capacity for intermittent renewables.
Increasing
levels of gas fired generation in emerging markets as they roll out
intermittent renewables
and;
New Independent
Service Provider (ISP) offerings which equal or exceed Original Equipment
Manufacturer (OEM) contract offerings.
OEM versus ISP LTSAs

Why an LTSA?
In the project finance structure of major power generation
facilities commercial lenders require an LTSA as a project key requirement to
satisfy the "bankability" of the project.
Originally the only party offering an LTSA to satisfy this
requirement was the Original Equipment Manufacturer (OEM).
However as the market has matured non OEM LTSAs have become
increasingly acceptable for new- build.
As original OEM LTSAs have reached break-contract or end of
contract milestones owners are looking at other options.
What Makes an LTSA Acceptable to lenders?
When a lenders Independent Engineer audits any LTSA either OEM
or ISP they look for a number of key elements to ensure the loan is secure:
LTSA Key Element 1
The "Back-to-Back"
Risk Wrap
The LTSA must have a "Back-to-Back" Risk Wrap.
This is a contractual mechanism designed to eliminate gaps in risk, liability,
and performance guarantees between two distinct phases (contracts) in a project
lifecycle
Phase 1 - the Engineering, Procurement, and Construction
(EPC) phase, under for example, FIDIC Silver Book contract framework
And;
Phase 2 - the operating phase under the LTSA contract.
Navigating the complex transition;
energy-i have successfully navigated and negotiated this
complex transition for multiple stakeholders, fully meeting the bankability
requirements of finance providers.
Options for owners - better LTSA terms;
energy-i pro-actively do this at an early stage, and even
if the owner ultimately decides to go down the OEM LTSA route rather than the
ISP LTSA route having options ensures better LTSA terms.
EPC and LTSA - key activities and milestones:
Under EPC contract frameworks, such as FIDIC Silver Book
there are a number of key contract milestones which are relevant may be wrapped
into the LTSA
These include;
Tests on Completion:
The Performance test and the Reliability Run as well as the
associated pre-commissioning and commissioning tests to ensure the plant meets
the performance criteria specified by the plant owner and the lender (Employers
Requirements)
Taking-Over / Taking-Over Certificate:
A full Acceptance Certificate (FAC) issued when the works
are complete, tested, and ready for use.
LTSA Key Element 2
Turbine Availability Guarantees
The LTSA must match the industry-standard Equivalent
Availability Factor (EAF) parameters (usually 92% to 95%+ availability) to
ensure predictable cash flow for debt service.
LTSA Key Element 3
Spare parts Sourcing and
availability
The LTSA must ensure access to a certified capital spare parts,
particularly hot gas path parts and ensuring the plant is protected against any
restrictive market controls e.g. hot gas path metallurgy

Scope split and issues to Watch
The split of cope
of activities between the owner and the LTSA provider is a key part of
negotiating or re-negotiating an LTSA
A typical scope
division for a standard Gas Turbine (CCGT and OCGT) Long Term Service Agreement
(LTSA) is set out below.
|
Phase & Activity |
Plant Owner |
LTSA Provider |
|
1. Program Management &
Engineering |
||
|
Turbine data analytics,
life-consumption tracking, & outage intervals |
Review & Approve |
Primary (Lead) |
|
Outage schedule optimization
& grid coordination |
Primary (Lead) |
Support |
|
Root Cause Analysis (RCA) for
covered component failures |
Support |
Primary (Lead) |
|
2. Parts Supply &
Refurbishment |
||
|
Supply of new/refurbished
capital parts (Buckets/Blades, Nozzles/Vanes) |
N/A |
Primary (Supply) |
|
Provision of consumables &
standard hardware (gaskets, nuts, bolts) |
Primary (Supply) |
Specification |
|
Off-site component repair,
advanced coatings, & metallurgical analysis |
N/A |
Primary (Execute) |
|
Ownership and disposal of
replaced capital parts (scrap metal value) |
Primary (Owns) |
N/A |
|
3. Outage Mobilisation &
Logistics |
||
|
Standard site cranes
(overhead/mobile) & heavy rigging equipment |
Primary (Supply) |
Specification |
|
Specialized rotor lifting
fixtures & OEM-specific tooling |
Support (Storage) |
Primary (Supply) |
|
Scaffolding, temporary power,
lighting, and breathing air |
Primary (Supply) |
N/A |
|
4. On-Site Outage Execution |
||
|
Technical Field Assistance
(TFA) & specialized engineering direction |
N/A |
Primary (Lead) |
|
Mechanical & electrical
craft labour (Turnkey approach) |
Optional (FTE Split) |
Primary (Provide) |
|
Lock-Out/Tag-Out (LOTO),
permit issuance, & balance-of-plant safety |
Primary (Owns) |
Compliance |
|
Rotor transport, shop
balancing, and de-stacking (if required) |
Logistics Support |
Primary (Execute) |
|
5. Commissioning &
Operational Support |
||
|
Gas turbine startup, grid
synchronization, and baseline operation |
Primary (Operate) |
Advisory |
|
Dry Low NOx (DLN) combustion
tuning & emissions verification |
Support |
Primary (Lead) |
|
Continuous 24/7 Remote
Monitoring & Diagnostics (M&D) |
Review alerts |
Primary (Continuous) |
Issues to watch;
Excluded Scope: Intake filters, exhaust ducting, generator
maintenance, balance of plant (BOP), and operational profile violations.
Liquidated Damages (LDs): Service provider caps
liabilities tied to Availability, Reliability, and Heat Rate performance
metrics, usually as a % of annual fee.